On the 24.04.2018, we had our eighth contract meeting with our client regarding any updates with the work.
As at 22.04.2018, we are currently at:
- Zero accidents or near misses.
- 20,721 man hours works.
- Fencing has been erected on Cab Road, entrance solely being used for Network Rail Employees.
- Monitoring vibration and noise levels near adjacent buildings.
- Removal of glazed bricks to commence.
- Site kept secure 24/7.