On the 27.03.2018, we had our sixth contract meeting with our client regarding any updates with the work.
As at 27.03.2018, we are currently at:
- Zero accidents or near misses.
- Fencing has been erected on Cab Road, entrance solely being used for Network Rail Employees.
- Demolition works began on the 26.03.2018.
- Perimeter hoarding to be erected 28.03.2018.
- Perimeter scaffolding to begin.
- Site cabins have been moved to the bottom of Salford Approach, with the gate house being relocated to accommodate the cabins.
- Car Parking to be moved onto Salford Approach.