On the 30.01.2018, we had our second contract meeting with our client regarding any updates with the work.
As at 30.01.2018, we are currently at:
- Flyers and business cards have been distributed (18.01.2018) to surrounding businesses. Regarding complaints, compliments and general updates which may affect them.
- Website is being updated fortnightly regarding each contract meeting.
- Zero accidents or near misses.
- Fencing has been erected on Cab Road, entrance solely being used for Network Rail Employees.
- Received licences to erect hoarding on Kings Head Yard and Greengate following demolition works.