On the 09.05.2018, we had our ninth contract meeting with our client regarding any updates with the work.
As at 09.05.2018, we are currently at:
- Zero accidents or near misses.
- 23,207 man hours works.
- Fencing has been erected on Cab Road, entrance solely being used for Network Rail Employees.
- Monitoring vibration levels.
- Removal of glazed bricks to commence.
- Demolition is under way.
- Site kept secure 24/7.